Project Resource Management
(Section 9 of the PMBOK® Guide)
145.Answer: D.
PMBOK® Guide, page 307, Introduction; and page 308, Figure 9-1
Project Resource Management Processes
Figure 9-1 provides an overview of the Project Resource Management processes, which are as follows:
9.1 Plan Resource Management—The process of defining how to estimate, acquire, manage, and utilize physical and team resources.
9.2 Estimate Activity Resources—The process of estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work.
9.3 Acquire Resources—The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
9.4 Develop ...