Errata
The errata list is a list of errors and their corrections that were found after the product was released. If the error was corrected in a later version or reprint the date of the correction will be displayed in the column titled "Date Corrected".
The following errata were submitted by our customers and approved as valid errors by the author or editor.
Color key: Serious technical mistake Minor technical mistake Language or formatting error Typo Question Note Update
Version | Location | Description | Submitted By | Date submitted | Date corrected |
---|---|---|---|---|---|
Printed | Page 16 the note at the end of the page |
No ebook study guide for the MCTS exam will be published. Please remove all the sentences after the first sentence in the note. |
Bonnie Biafore |
Apr 20, 2011 | |
Printed | Page 74 Item number 3, first paragraph, second line |
The text says, "It also shows up in the Gantt chart above the task's task bar ..." Shouldn't above" should be "next to"? The resource name appaers next to the task bar, as shown in Figure 3-9 and in the description accompanying Figure 309. Note from the Author or Editor: |
Rose Aquila | Dec 02, 2010 | |
Printed | Page 88 Power User's Clinic |
The paragraph entitled 'Displaying a WBS in a Hierarchy' references the "WBS Modeler" and that it is for Visio Professional (2007 or 2010). This is incorrect... it does NOT work if you are using Project 2010. In fact you will wind up with a disk problem... but chkdsk will not be able to run if you download this utility. You will have remove it manually, if you can find it. Note from the Author or Editor: |
Tom Bonadio | Sep 22, 2010 | |
Mobi | Page 110 Figure 5-2 |
In Figure 5-2, the "Work packages" filter is shown with "Duration does not equal 0d". However, if you have created your tasks as manually scheduled, then all of the work package tasks will have a duration that evaluated to "0d" (even though they show as blank). This is problematic since the supposed reason the user is exporting the spreadsheet is to get estimates from team members. Changing the filter to "Scheduled Duration does not equal 0d" fixes the problem--all Milestones will have Scheduled Duration of 0d, and all work packages will have 1d. Note from the Author or Editor: |
Owen Magee | Nov 15, 2012 | |
Printed | Page 220 Table 9-1 |
Why are the lines 4 and 6 identical in Table 9.1? (Duration: "Your input", Work: "Project calculates", Units: "If blank, Project uses 100% of Max. Units") Note from the Author or Editor: |
Anonymous | Dec 30, 2012 | |
Printed | Page 224 Table 9-2. Fixed durationtask type, effort-driven schedulign turned on |
The table indicates that for a fixed duration task adding a resource when effort-driven sceduling is truned on causes the units to decrease for each resource. However, when I try this, the work changes for each resource and the units stay the same. Do you know why? Note from the Author or Editor: |
Philly Rose | Dec 22, 2010 | |
Printed | Page 410-411 3rd bullet. |
The author mentions errata correcting third bullet from the bottom on page 410. In my book, that is page 411. isbn:978-1-449-38195-0 Note from the Author or Editor: |
Anonymous | Jul 25, 2011 | |
Printed | Page 411 3rd bullet from bottom of page |
The Show slack bullet point says to turn on the Critical Tasks checkbox. It should say "turn on the Slack checkbox" |
Bonnie Biafore |
Jan 04, 2011 | |
Other Digital Version | 11650 Kindle location 11650 |
Paragraph beginning "To use Physical % Complete..." 3rd sentence should begin 'Under "Earned Value options for this project"...' instead of 'Under "Calculation options for this project"...' Note from the Author or Editor: |
Darin Davis | Nov 13, 2012 |