Errata for Microsoft Project 2010: The Missing Manual
Submit your own errata for this product.
The errata list is a list of errors and their corrections that were found after the product was released. If the error was corrected in a later version or reprint the date of the correction will be displayed in the column titled "Date Corrected".
The following errata were submitted by our customers and approved as valid errors by the author or editor.
Color Key: Serious Technical Mistake Minor Technical Mistake Language or formatting error Typo Question Note Update
| Version |
Location |
Description |
Submitted By |
Date Submitted |
Date Corrected |
| Printed |
Page 16
the note at the end of the page |
No ebook study guide for the MCTS exam will be published. Please remove all the sentences after the first sentence in the note.
|
 Bonnie Biafore
 |
Apr 20, 2011 |
|
| Printed |
Page 74
Item number 3, first paragraph, second line |
The text says, "It also shows up in the Gantt chart above the task's task bar ..." Shouldn't above" should be "next to"? The resource name appaers next to the task bar, as shown in Figure 3-9 and in the description accompanying Figure 309.
Note from the Author or Editor: "above" should be "next to"
|
PhillyRose |
Dec 02, 2010 |
|
| Printed |
Page 88
Power User's Clinic |
The paragraph entitled 'Displaying a WBS in a Hierarchy' references the "WBS Modeler" and that it is for Visio Professional (2007 or 2010). This is incorrect... it does NOT work if you are using Project 2010. In fact you will wind up with a disk problem... but chkdsk will not be able to run if you download this utility. You will have remove it manually, if you can find it.
Note from the Author or Editor: In the sidebar on page 88, delete the second paragraph that talks about the Visio WBS Modeler. Then in the next paragraph, delete the word "also".
|
Tom Bonadio |
Sep 22, 2010 |
|
| Printed |
Page 224
Table 9-2. Fixed durationtask type, effort-driven schedulign turned on |
The table indicates that for a fixed duration task adding a resource when effort-driven sceduling is truned on causes the units to decrease for each resource. However, when I try this, the work changes for each resource and the units stay the same. Do you know why?
Note from the Author or Editor: When editing a task that already has work completed, Project keeps track of another field called peak units. So, it now remembers the original assigned units for the task as well as higher units to complete the task in the timeframe.
|
Philly Rose |
Dec 22, 2010 |
|
| Printed |
Page 410-411
3rd bullet. |
The author mentions errata correcting third bullet from the bottom on page 410. In my book, that is page 411. isbn:978-1-449-38195-0
Easily found. Thanks.
Note from the Author or Editor: yes indeed, it is on page 411
|
Anonymous |
Jul 25, 2011 |
|
| Printed |
Page 411
3rd bullet from bottom of page |
The Show slack bullet point says to turn on the Critical Tasks checkbox. It should say "turn on the Slack checkbox"
|
 Bonnie Biafore
 |
Jan 04, 2011 |
|
|
| |