TIME PROCESS4Activity Sequencing (PMBOK® 6.2, Sequence Activities)

What:

Determining dependencies among project activities.

When:

Project planning.

Results:

A graphical or tabular summary of project workflow.

Review Project Data

Activity sequencing is generally done in parallel with activity duration estimating and activity resource estimating during project plan development. Sequencing is a bottom-up planning process, not based on fixed-date or arbitrarily imposed top-down deadlines. Significant plan variances against project timing objectives are best resolved through constraint management and plan optimization and negotiating project changes.

To begin, assemble project milestone and activity definition data, along with other project ...