CHAPTER 10Realistic Scheduling

INTRODUCTION

If you ask people what makes a project successful, “a realistic schedule” usually tops the list. But ask them to be more specific, and several characteristics of a realistic schedule emerge. A realistic schedule:

  • Includes a detailed knowledge of the work to be done.
  • Has task sequences in the correct order.
  • Accounts for external constraints beyond the control of the team.
  • Can be accomplished on time, given the availability of skilled people and enough equipment.

Finally, a realistic schedule takes into consideration all the objectives of the project. For example, a schedule may be just right for the project team, but if it misses the customer's completion date by a mile, then it's clear that the whole project will need to be reassessed. Building a project plan that includes all the necessary parts and achieves a realistic balance among cost, scheduling, and scope requires a careful, step‐by‐step process.

Chapter 9 dealt with the first step in planning the project: the work breakdown structure. This chapter explains planning steps two through five. Each planning step relies on the one preceding it, and each adds a new element to the plan. You can use the diagram shown in Figure 9.1 as a guide in this chapter.

A Key Leadership Opportunity

Once you've mastered the techniques in this chapter, building a realistic schedule can seem like basic math. That's your opportunity. Prior to using this step‐by‐step, bottom‐up scheduling technique, ...

Get The Fast Forward MBA in Project Management, 6th Edition now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.