Formatting the Resource Graph View
The Resource Graph view shows values derived from the task assignments of one or more resources; these values are graphed along a timescale. To display the Resource Graph view, choose View, Resource Graph or click the Resource Graph icon on the View bar. Figure 20.33 shows a histogram, or bar chart (in the lower pane), for the allocated and overallocated task assignments for Mary Logan during the weeks of September 22 through November 10. The value displayed in this example is the peak units, or percentage of effort assigned during each time period (in this case, each week).
Figure 20.33. The Resource Graph view, showing peak units, can be displayed below the Resource Usage view.
→ For more information about ...