Understanding the Driver Resource Concept
The various changes in assignments described so far in this chapter produce changes in assignments and in the task duration. It helps to understand the changes in assignments if you understand the concept of the driver resource.
The term driver resource is used to identify resources whose assignments determine the duration or finish date for the task. Recall that when there are multiple resources assigned to a task, the task duration is at least as long as the longest assignment. The resources with the longest assignments are the driver resources. Other resources whose assignments finish earlier are nondriver resources. Anything that causes a driver resource’s assignment to finish later causes the task ...
Get Special Edition Using Microsoft® Project 2002 now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.