Understanding the Work Formula
As described previously in this chapter, Project uses assignment units as a multiplier to calculate how much work it must schedule. When you assign two carpenters (200%) to work on a task with a duration of 4 hours, Project schedules 2 hours of work for each of the 4 hours of duration. The total work is therefore 8 hours.
The formula for calculating work is as follows:
In symbols, it is represented as follows:
That is, you multiply the task duration by the assigned units to calculate work.
NOTE
These formulas ...
Get Special Edition Using Microsoft® Project 2002 now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.