Troubleshooting

Start Times Don’t Match

I’ve changed my default start time to be 7:00 a.m. and coordinated this change with my Standard calendar, but my first task is still starting at 8:00 a.m. What’s wrong?

If you choose Project, Project Information, you’ll notice that the project starts at 8:00 a.m. This start time occurs because when you initially entered the project start date (in the Project Information dialog box) or accepted the default time, Project also assumed that this was the start time. The work time for the project was set to the hours of 8:00 a.m. to 5:00 p.m. You later made changes to the Calendar tab of the Options dialog box, but changes in this dialog box are not retroactive; you also have to change the start time for the ...