Project Schedule Management
(Section 6 of the PMBOK® Guide)
78.In rolling wave planning:
A.Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.
B.The work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher level.
C.The work far in the future is planned in detail for work packages that are at a low level of the WBS.
D.A wave of detailed activities is planned during strategic planning to ensure that WBS deliverables and project milestones are achieved.
79.The precedence diagramming method (PDM) is:
A.A technique in which activities are represented by nodes and are graphically linked by one or more logical ...