Project Communications Management
(Section 10 of the PMBOK® Guide)
164.Answer: A.
PMBOK® Guide, pages 359–360, Introduction; and page 360, Figure 10-1
Project Communications Management
Figure 10-1 provides an overview of the Project Communications Management processes, which are as follows:
10.1 Plan Communications Management—The process of developing an appropriate approach and plan for project communications based on stakeholders’ information needs and requirements, and available organizational assets.
10.2 Manage Communications—The process of creating, collecting, distributing, storing, retrieving, and the ultimate disposition of project information in accordance with the communications management plan.
10.3 Monitor Communications—The process ...