Chapter 2

Definitions of Maturity Levels

The levels of the PM Solutions Project Management Maturity Model are as follows:

Level 1: Initial Process

Although there is a recognition that project management processes exist, there are no established practices or standards, and individual project managers are not held to specific accountability by any process standards. Documentation is loose and ad hoc. Management understands the definition of a project, that there are accepted processes, and is aware of the need for project management. Metrics are informally collected on an ad hoc basis.

Level 2: Structured Process and Standards

Many project management processes exist within the organization, but they are not considered organizational standards. ...