Sample questions
1 |
1. Which of the following best defines a contingency action?
(a) An activity that is planned to take place if a risk materializes. (b) An action taken at the start of a project which reduces the potential damage if a certain risk does materialize. (c) An agreement that the users accept a particular risk. (d) An activity which prevents a risk from materializing. |
2 |
2. What is maintenance of a risk log designed to do?
(a) eliminate risk; (b) save money; (c) control risk; (d) prevent system development failure. |
3 |
3. Which of the lists below best identifies what is examined when a risk is assessed?
(a) Probability, proximity, owner (b) Impact, probability, team experience (c) Cost, benefit, business case (d) Probability, ... |