1. The change control board should consist of:
(a) representatives of the key stakeholders in the project; (b) the project manager and team leader; (c) the people on the project board; (d) the project support office. |
2 |
2. If there are doubts about the projected costs of a proposed change, it would be the responsibility of which of the following to investigate?
(a) the change requestor; (b) the change manager; (c) the change feasibility group; (d) the change control board. |
3 |
3. As a documented procedure, what is the purpose of configuration management?
(a) to ensure the project remains within budget; (b) to identify and document functional characteristics of a system; (c) to record and report changes and their implementation ... |