Sample questions
Questions 1, 2 and 3 are about the diagram below. The number of days shown in each box is the duration of the activity.
1 |
1. Which of the following is the critical path?
(a) A, B, D, G (b) A, B, E, G (c) A, C, E, G (d) A, C, F, G |
2 |
2. What is the float for activity F?
(a) 0 days (b) 2 days (c) 4 days (d) 6 days |
3 |
3. Activities B and C have to be completed by the same person. What is the delay in the end time of the project?
(a) 3 days (b) 5 days (c) 4 days (d) 1 day |
4 |
4. Which of the following does not take account of the dependencies between activities?
(a) Gantt chart (b) activity network (c) work breakdown structure ... |