Quick Reference Formulas for Project Management
(More comprehensive formulas are provided in Appendix A)
PERT time:
PERT time variance:
Earliest start (ES) time for Activity i:
Earliest completion (EC) time of Activity i: EC(i) = ES(i) + ti
Earliest completion time of a project: EC(Project) = EC(n), n is the last node.
Latest completion (LC) time of a project: LC(Project) = EC(Project), with no deadline
Latest completion (LC) time of a project: LC(Project) = Tp (deadline)
Latest completion (LC) time for activity i:
Latest start time for activity i: LS(i) = LC(i) − ti
Total Slack (TS): TS(i) = LC(i) − EC(i); TS(i) = LS(i) − ES(i)
Free Slack (FS):