Chapter 11. Answers to Practice Exam 1
1. B
2. C
3. A
4. A
5. D
6. C
7. D
8. A
9. A
10. D
11. D
12. A
13. C
14. A
15. D
16. D
17. A
18. D
19. A
20. A
21. B
22. A
23. A
24. A
25. C
26. B
27. D
28. A
29. C
30. A
31. A
32. B
33. A
34. A
35. A
36. D
37. A
38. C
39. A
40. D
41. A
42. A
43. A
44. B
45. A
46. C
47. C
48. B
49. B
50. B
Question 1 | Answer B is correct. The scope statement is an output of scope planning (5.2 PMBOK), which is part of the overall Planning phase. Answer A is incorrect because concept is another term for initiation. Answers C and D are incorrect because they are not official names of project phases. |
Question 2 | Answer C is correct. A WBS is not a project scheduling method. |
Question 3 | Answer A is correct. As a project progresses ... |