15.27. Handling of licensed process
Where a licensed process or basic design should be prepared by a Licenser, the Contractor's scope of work concerning the completion of the P&ID will be dependent on the type of contract with the Licenser and Contractor.
15.27.1. Licensing contract via the contractor
In this case, the Contractor and the Licenser jointly and severally shall give a process performance guarantee to the Company.
• Case 1: licenser prepares P&ID
The P&ID supplied by the Licenser shall be equivalent to the “P&ID for piping layout” given in this section, and shall contain all design philosophies concerning process. The Contractor shall carry out mainly the following activities:
• prior to the Licenser's commencing the preparation of the ...