Representing Project Data in a Visio Diagram
If you decide to build a project directly in Visio, or if you plan to export Microsoft Project information to a Visio diagram, it’s helpful to understand how the four Visio templates for schedules work. The templates that apply to projects or other date-related information include the following:
Timeline. The Timeline template displays tasks and events in a way that Microsoft Project does not. It shows them along a horizontal or vertical bar. This can be useful, for example, to summarize the phases of a multiyear project and key milestones toward its completion.
Gantt Chart. Although you can use Visio to build simple Gantt charts, it is more useful as a presentation tool when you’re using data exported ...
Get Microsoft® Office Project 2007 Inside Out now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.