Rearranging Your Project Information
The ability to switch from one view to another, to switch tables in a sheet view, and to add or remove fields in a view gives you tremendous versatility in how you see your project information. You can take it a step further by sorting, grouping, and filtering the information in a view.
Sorting Project Information
By sorting information in a table, you can arrange it in alphabetical or numerical order by a particular field. For example, you might sort your tasks by start date so you can see tasks that are due to start next week. Or you might sort your tasks by duration so you can see the tasks with the longest durations and how you might break them up and bring in the project finish date.
You can also sort resources. ...