Errata

SharePoint for Project Management

Errata for SharePoint for Project Management

Submit your own errata for this product.

The errata list is a list of errors and their corrections that were found after the product was released. If the error was corrected in a later version or reprint the date of the correction will be displayed in the column titled "Date Corrected".

The following errata were submitted by our customers and approved as valid errors by the author or editor.

Color key: Serious technical mistake Minor technical mistake Language or formatting error Typo Question Note Update

Version Location Description Submitted By Date submitted Date corrected
Printed
Page 43
at the bottom

On page 43, at the bottom, there should be 3 more steps after step 2
"Under columns, click Title"

Here they are:
3. Rename the column Title to Resource Name.

4. Click OK.

5. Under Columns section of the page, click Create column.

Note from the Author or Editor:
on page 43, after step 2, add the following 3 steps:

i. Rename the column Title to Resource Name.

ii. Click OK.

iii. Under Columns section of the page, click Create column.

Anonymous  Oct 23, 2008  Jul 01, 2009
PDF
Page 126
1

From the Cafe Project Tasks list, select Actions→Show in Standard View. A page
similar to the one shown in Figure 6-13 will be displayed.

I do not find a "Cafe Project Tasks list" created in chapters before. Where is the logical predecessor of paragraph 10.? A calendar view is described here which never has been created before. I do not know, what you are speaking about here.
Would be kind to have an idea where figures 6-13 and 6-14 is derived from in the descriptions.

Hans Willi

Note from the Author or Editor:
P. 126, Step 10, the word "Cafe" should be removed from "Cafe Project Tasks list".